PROJECT UPDATES · 12.2025
Fiber optic backbone for 10G, energized in Pasay City
Forty-eight strands terminated, tested, and turned over in 21 days. The full write-up covers the pull schedule, the splice plan, and the OTDR results.
READ THE ARTICLE ↓
PROJECT UPDATES · 03.2026
FDAS and electrical works turned over at Tiarra Restobar
Addressable fire detection and electrical fit-out for a Bulacan hospitality site.
TECHNICAL NOTES · 09.2025
What the Permit to Operate process actually involves
From load schedule to inspection, signed and sealed by our in-house PEE. Clark facility case.
PROJECT UPDATES · 07.2026
Vermosa phase two: access control and CCTV rough-in starts
Containment shared with the SCS tray plan, device locations locked on one drawing set.
COMPANY · 02.2026
Two more installers certified on CommScope Systimax
Manufacturer certification keeps the 25-year system warranty available to our clients.
TECHNICAL NOTES · 11.2025
FM200 or NOVEC: choosing a clean agent for server rooms
Agent choice, cylinder sizing, and the maintenance schedule that keeps it compliant.
ARTICLE VIEW · POST 2025-12-04
PROJECT UPDATES · PASAY CITY · 12.2025

Fiber optic backbone for 10G, energized in Pasay City

BY ENGINEERING TEAM
·
4 MIN READ
·
FOC / OTDR / FUSION
SPLICE TRAY, TELECOM ROOM B · PASAY CITY · 12.2025

A BPO client in Pasay City needed its building backbone upgraded from 1G to 10G without interrupting a floor that runs 24 hours. The building riser carried a mix of legacy multimode and copper trunks, none of it certified for the new load.

We ran forty-eight strands of single-mode fiber up the riser on new containment, spliced at each telecom room, and terminated on pre-labeled LC panels. Pulls were scheduled between 10 PM and 5 AM. Agents kept working; the old plant stayed live until cutover night.

Every strand was OTDR tested in both directions. The worst measured loss on the longest run came in well under the budget for 10G, and the full result set went into the turnover binder beside the as-built riser diagram.

48
strands installed
21
days to turnover
0
hours of floor downtime
100%
of strands OTDR tested